KORRO AQUA 2741
Prefabrication primer
- Corrosion protective
- 1-component
- Water-borne
- Prefabrication primer
KORRO AQUA 2741 is a 1-pack prefabrication primer based on acrylate dispersion.
As a temporary protection on blast-cleaned steel. KORRO AQUA 2741 can be topcoated by many 1-pack and 2-pack paints, such as water-borne acrylate, epoxy and polyurethane paints, solvent-borne epoxy and polyurethane paints, and xylene-dilutable alkyd paints.
Technical data sheet
Safety data sheet
Other product specific documents
Surface preparation
Remove from the surfaces any contaminants that might be detrimental to surface preparation and application. Remove also water-soluble salts by using appropriate methods. The surfaces are prepared according to the different materials as follows:
STEEL SURFACES: Remove mill scale and rust by blast cleaning to preparation grade Sa 2½ (standard ISO 8501-1).
Additional instructive information for surface preparation can be found in standards EN ISO 12944-4 and ISO 8501-2.
Application
Stir thoroughly before use.
Apply as evenly as possible. The best result is achieved by an automatic airless spray. Suitable airless nozzle size 0.015 - 0.021".
Application conditions
The surface to be treated must be dry. During the application and drying period the temperature of the ambient air, the surface and the product shall be above +15°C and the relative air humidity below 70%. Additionally, the temperature of the surface to be treated and the product must be at least +3°C above the dew point of the ambient air.
Especially when applying with a spray the relative air humidity should be above 30% to avoid the onset of the drying process to be too fast.
Surface temperature, film thickness, drying temperature and ventilation affect the drying of the paint. The paint is dry when all water has evaporated from the paint film. It is essential that all painted surfaces have sufficient ventilation. If the painted surface will be exposed to weathering, moisture or low temperatures (below +10°C) thick paint films are to be avoided and the last coat must be allowed to dry for at least 24 hours (at +23°C) before exposure. Low temperatures and insufficient ventilation slow down the drying process.
Storage
The storage stability is shown on the label. Store in a cool place and in tightly closed containers. Do not transport or store at temperatures below 0°C.
Must not freeze.
Total mass of solids | abt. 650 g/l |
---|---|
Volatile organic compound (VOC) | abt. 35 g/l |
Gloss | Matt |
Theoretical spreading rate | The typical nominal film thickness 20 μm is equivalent to a wet film thickness of 53 μm on a smooth surface. The theoretical spreading rate is then 19 m²/l, see standard EN 10238. |
Practical spreading rate | In practice, the spreading rate on surfaces prepared by blast-cleaning has been found to be between 10 - 14 m²/l. |
Drying time – dust free | 1 - 3 min (ISO 9117-3:2010) |
Drying time – touch dry | 5 min (ISO 9117-5:2012) |
Thinner | Water. |
Clean up | Water. Cleaning of the equipment: When painting equipment used for application of solvent-borne paints is used for water-borne paints the equipment must be cleaned carefully: 1. Wash with solvent. 2. Wash with washing solvent for water-borne paints, e.g. TEKNOSOLV 6060. 3. Rinse with water. When shifting from water-borne to solvent-borne paints act in reverse order. |
Colours | Red. Other colours by agreement. |
Safety markings | See safety data sheet. |